Tender SURE Phase 1- Project status report
January 09, 2014• By Team Icmyc
December 23, 2013 – December 28, 2013
SUMMARY
• 4 trial pits at St. Marks road
• Carriageway and centreline marking of St. Marks road.
• Carriageway and centreline marking of Cunningham road.
DAILY WORK PERFORMED
• 23.12.2013 – St. Marks road carriageway and centreline marking.
• 24.12.2013 – St. Marks road carriageway and centreline marking.
• 25.12.2013 - St. Marks road centreline and carriage width marking with nails. 1 trail pit at St. Marks road.
• 26.12.2013 - St. Marks road centreline and carriage width marking with nails. 2 trail pits and utility scanning at St. Marks road.
• 27.12.2013 - Cunningham road centreline and carriage width marking with nails. 1 trail pit and utility scanning at St. Marks road.
• 28.12.2013 - Cunningham road centreline and carriage width marking with nails. 1 trail pit and utility scanning at Vittal Mallya road.
WORK PLANNED FOR THIS WEEK
• Invert level - All roads
• Road marking – Cunningham road
• Trial pit – Cunningham road
ISSUES/ACTION
• Invert levels of all the 7 roads are required for storm water and sewage water drawing.